- In delivery
- 3
- 1 paused for non-payment
- Off track
- 2
- reason shown to the client
- Client approvals overdue
- 3
- each one can move a launch date
- Invoices overdue
- 2
- finance chases; lead is told
| Project | Health | Stage | Scope done | Effort used | Waiting on client | Paid of price | Lead |
|---|---|---|---|---|---|---|---|
| Field service app BS-1047 · Najd Field Services | Off track updated 25 Nov | Cycle 2 of 7 Launch: 15 Feb 2027 | 20% 47 of 231 days | 2 approvals1 invoice | 79,200 of 264,000 | OROmar | |
| Loyalty and ordering BS-1050 · Qimma Retail | Off track updated 15 Nov | Paused in cycle 3 Launch: To be re-planned | 28% 58 of 204 days | 1 invoice | 68,400 of 228,000 | OROmar | |
| Clinic booking BS-1042 · Dar Al Shifa Clinics | At risk updated 23 Nov | Cycle 5 of 8 Launch: 25 Jan 2027 | 56% 151 of 268 days | 1 approval | 156,000 of 326,000 | OROmar |
Effort used turns red when it runs more than 10 points ahead of scope done: the project is spending faster than it is finishing.