BS-1042 · Dar Al Shifa Clinics · scope v4 · Cycle 5 of 8

At risk

Health: At riskset by Omar Rahman, 23 Nov · next update due Mon 30 Nov

Payment gateway onboarding is waiting on the client's bank documents. Launch date holds if they arrive by 4 Dec.

The client sees this status and this sentence on their overview. If we do not update it by Monday it shows “Update missing” to both sides.

Scope done
52%
by cards the client has accepted
Effort used
56%
151 of 268 reviewed days
Next demo
3 Dec, 11:00
Target launch: 25 Jan 2027
Paid
156,000
of 326,000 AED

Waiting on the client

Overdue items move the launch date. The portal tells the client by how much.

  • Approve the doctor schedule screenOverdue since 24 Nov
  • Decide on CR-2 (price valid until 10 Dec)Due 10 Dec

Waiting on us

Reply promise: within 48 hours on working days (Monday to Friday, Gulf time).

  • Reply to Mariam: "Can reception see tomorrow's bookings on a phone?"31 working hours left

Staging: staging.daralshifa.example · last release notes sent 19 Nov · QA sign-off by Hana Yusuf on build 0.5.2